Date

Responsibility

Action / Deliverables

 

Infrastructure Team

Maintenance screen to be raised in Production once Content Release Lead confirms content cut off is complete (they will request this via Infra ticket)

 

Development TeamCheck that inferred relationship coming from Snomed Release Service match those in Snowstorm to avoid large and unnecessary data reconciliation effort.

 

Development Team

Run MRCM Validator manually, in order to verify MRCM Refsets themselves (content is now automatically validated against the MRCM as part of RVF). Run the dailybuild locally and no issues found. MAINT-1297 has merged the refset validations and will be released in 6.7


Development TeamChecks to be completed in order to ensure that there are no concepts in the termServer that were promoted by the authors, but yet somehow didn’t make it into MAIN ready for versioning (as has happened before)
 

 

Infrastructure Team

 

Infrastructure TeamOnce the mapping team have finalised the maps, update the Daily Build/Mapping Drip feed

 

Infrastructure TeamProvisional date to drop Maintenance screen and re-open Content authoring for next editing cycle

 

Infrastructure TeamOnce Release Manager sends proposed Alpha release package, run the test upload into Prod browser to ensure no issues.

 

Rory / Infrastructure Team ?Run a classification of a new, clean US project in order to double check there are no classification results. In the past this has identified issues that otherwise would have been found until too late in the Release cycle.

Infrastructure TeamCreate a new, separate version of the browser with the provisional Beta release package as a baseline. This is to allow the Content Team to verify that all of the Alpha fixes have been applied correctly, & haven't had any adverse impacts.

 

Infrastructure TeamOnce Release Manager sends proposed Beta release package, run the test upload into Prod browser to ensure no issues.

 

Infrastructure TeamOnce Release Manager sends proposed Member release package, run the test upload into Prod browser to ensure no issues.

Infrastructure TeamCreate a new, separate version of the browser with the provisional Member release package as a baseline. This is to allow the Content Team to verify that all of the Alpha + Beta fixes have been applied correctly, & haven't had any adverse impacts.

 

Development Team

Merge all Alpha/Beta fixes into the original Release branch

OLD PROCESS (Kai Kewley / Michael Chu please confirm new SnowStorm process?):

  • Export Release feedback fixes from main/RFJ branch

  • Import Release feedback fixes into the MAIN/[release date]/[fix branch]

  • Promote Fix branch to Release branch for Release Manager to run Production release build

  • Build and test Production release
    a) If all clean then use the new Release branch for final Production Public release
    b) If major issues then revert back to Fix branch for final Production Public release

  • XXX AMI update no longer required XXX

  • Dev-Ops create a new Snapshot export from MAIN/[release date] in Prod termServer

  • Dev-Ops update the classification service using the snapshot export

  • Compare release fixes with MAIN delta export to create a consolidated RF2 delta

  • Import RF2 delta into MAIN/[release date]/[fix branch]

  • Run classifications and validation before promoting MAIN/[release date]/[fix branch] into MAIN

    Andrew Atkinson I don't think these steps are the old process either. e.g We can't promote MAIN/[release date]/[fix branch] into MAIN. Please ignore these. I will have a chat with Kai Kewley to document the new process as he did all the work in the last release.

 

Development Team

Once Release Manager confirms Production release is deployed to S3, RVF auto-scaling images to be rebuilt

please confirm new SnowStorm process - is this still required?

It no longer requires an AMI update for new Snomed releases. Please remove this step in future releases.

 

Development Team

Once Release Manager confirms Production release is published, update both the

 

Development Team

Once Release Manager confirms Production release is published:

  • Merge any and all Feedback fixes back into MAIN (eg) INFRA-4790 - Getting issue details... STATUS
  • Ask the content team to verify everything is as expected in MAIN, according to their intentions when authoring the fixes

 

Infrastructure Team

Once Release Manager confirms Production release is published, update all Production systems (browser, website, etc) using the final S3 published package.

From September 2020 ensure that the GPS ValueSet is available through the FHIR API ie https://browser.ihtsdotools.org/fhir/ValueSet/gps