In this page:
How to promote a non-complex task (one without SAC / AAG controls) to include its changes in the parent project. This process updates the project level with concepts created or modified in the task, which can then be taken into other tasks via their rebase from the project, and also promoted to MAIN via the project, for inclusion in the next SNOMED CT release.
Steps | References |
---|---|
Press Promote This Task to the Project in the Task View - Task Details panel actions button list | |
A "Preparing for task promotion" notification is presented in the page header. | |
Task promotion has implicit warning checks for the following conditions:
If no content has been changed on the task when promotion is initiated, a Promote Task pop-up notification states the there are no changes to promote. Press If content changes have been made but any of the other conditions are not yet satisfied when promotion is initiated, a Promote Task pop-up notification shows their statuses, with action options to cancel the promotion, or to continue if task changes are considered sufficiently safe to update the project level content without satisfying these conditions. Press Press Promoting tasks despite warnings
Promoting unclassified content changes is a quality assurance risk that can be avoided relatively easily, since it typically takes less than ten minutes to run classification (if only to confirm no results). However there are occasions when it is clear that inferred classification results won't change, such as a description-only content change, in which case this option may save a little time if needed. By-passing review is another scenario where this option can save time, for instance if the author is also implicitly the reviewer or perhaps the project manager / project lead. Note that this scenario won't be feasible if the task is made into a Complex task and Review Completed is also set as a mandatory task-level SAC requirement within its parent project configuration, since promotion can't be enabled without a completed review in this case. |
|
A "Promoting task..." notification is presented in the page header whilst branch content changes are merged to the project level. During promotion, the task content branch is locked to prevent any further changes, and a warning notification is presented below the | |
Once task promotion is completed, a "Task successfully promoted for PROJECT-##" notification (where PROJECT-## is the task identifier) is presented in the page header. Following promotion no further changes are allowed on the task content branch, all action buttons in the Task Details panel become inactive, and a warning notification is presented below the now inactive |