Date | Deliverables |
---|---|
| Authoring begins for the January 2019 International Edition editing cycle. |
17 | Content team to deliver final MRCM change requests to Linda for action |
22 Aug | Linda delivers MRCM changes to content team for review - Content Team to complete this by 28 Aug 28 Aug |
| Content team to deliver final reviewed MRCM changes plus any feedback to Linda |
28 Aug | Linda to make any necessary changes (based on feedback from the authors) - Linda to complete this (and verify with Yong) by 31 Aug |
31 Aug | NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. |
03 |
|
|
|
|
|
|
|
| Content team review, rebase and finalise all content |
| Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) |
| Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
| Final content review (2 days) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement. |
|
|
|
|
|
|
|
|
|
|
Handover of Release Notes to technical team Release manager (Andrew) | |
| PLANNED Alpha Release date |
| PLANNED Alpha feedback deadline |
| PLANNED BETA Release date |
| PLANNED BETA feedback deadline |
| Member Release date |
| Public Release date |
...