  team review, rebase and finalise all contentMaria BraithwaiteMaria BraithwaiteMaria Braithwaite

Farzaneh Ashrafi + Suzanne Santamaria

Maria Braithwaite
  • CONTENT CUTOFF DATE (12:00 UTC), +
  • Handover of content to technical team Release manager
  • Content Release Lead to request (via Infra ticket) the maintenance screen to be raised in Production, to prevent further updates to International content - Technical Team Release tasks - July 2020 8th  
     MAPPING CUTOFF DATE (12:00 UTC), + Release Notes to technical team Release manager (Note: recheck final figures for concept changes/ additions etc before member release and public release to take into account changes made after close of editing).
    DateResponsibilityDeliverables

     

    Authoring begins for August 2021 International Release.

      

    No further batch loads or bulk updates.

    No further promotion for projects that have large scale changes for example promotion from the Community Content or changes to foundational hierarchies likely to have impact across other content.

     


    Last day to launch a new task in the authoring platform intended for the current release cycle.

    Maria Braithwaite

    Last day for the Content team to promote any changes intended for release in the current editing cycle.

    Content review for conflict with LOINC agreement.

    Maria Braithwaite

    Lockdown of project promotion.

    Planned initial handover meeting (if required).

    Restart content editing for the next release cycle in the new release branch.

    Maria Braithwaite Content

     

    Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency)

      

    Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project (Internal Quality Assurance - INTQA) - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover.

     

    Final content review (2 days)

    Request vet extension report

    Request QI content changes report

    Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement

     

    release manager final content review and validation in the current release branch.

    Handover of content to Technical team release manager.

    Final handover meeting.

    Technical team release tasks.

    Reminder to WCI to cut off mapping drip feed (but NOT clone over to Release Server until Mapping Team confirms that both ICD-0/ICD-10 + GMDN maps are all updated based on

    Content + latest GMDN content

     

    Planned Initial Handover meeting

    .

    Donna Morgan

    Mapping Team to notify WCI mapping/review ready for QA.

    QA of mapping (Mapping Team + WCI)

    .

     

    Terance Shird

    termServer branching and Release versioning

    Technical Team Release tasks - August 2021 

    .

    Andrew Atkinson

    Full validation of the initial exported

    content 

     

    • Content Team to confirm that Lateralizable refset is complete in Production refset tool (Release manager to then action the refset tool release to get the delta files), +
    • Content Team to deliver the SEP refsets (x2) to Release manager

    content.

    Lateralizable and SEP ref sets. (BUT ONLY IF NEW AUTOMATION OF THESE REFSETS IS STILL NOT YET AVAILABLE).

     

    Maria Braithwaite

    Mapping/Review/Technical QA complete

    Authors and mappers - Preparation of

    .

    Preparation of release notes

    content 

    .

    Mapping team to request Clone of Mapping content (both ICD-0/ICD-10 + GMDN) over to the Release Server, in order to provide a stable baseline for both upcoming International + GMDN releases.

    Handover of ICD-0 + ICD-10 maps to technical team Release manager (Andrew Atkinson)

    Restart the mapping Drip Feed.

    Maria BraithwaiteHandover of

     

    • Planned Final Handover meeting, +

    • PLANNED Alpha Release date (internal only + possibly Australia as well?)
    • Provisional date for Content authoring starts for next editing cycle

     

    PLANNED BETA Release date

    Restart the mapping Drip Feed - this can actually be done earlier than the final Beta if required, as the only pre-requisite is to complete the ICD-0/ICD-10 testing in the Beta build. This is simply to provide confidence that there will not likely be map changes during the Alpha/Beta stage, which could in theory create re-work for the teams. This risk should be balanced against the growing backlog of map changes, and a decision made whether to use an early Beta build to switch the drip feed back on.

    Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle)

     

    PLANNED BETA feedback deadline 

     

    Member Release date

    release notes to Technical release manager.

    Andrew Atkinson

    Production public release date.

     

    PRODUCTION Public Release date