Date

Time (UTC)

Responsibility

Action / Deliverables

 

12:00DevopsSetup new automated JIRA tickets to be generated from the parent International Release ticket, for all Mapping steps below (both internal and external)

 

18:00

WCI (External Team)

INITIAL MAPPING CUTOFF

*** DRIP FEED SUSPENDED from this point onwards ***

 

02:00

WCI (External Team)

Cron job to completely remove SNOMED + upload the latest version to the Release Mapping Server.

In future, this should happen immediately after the Daily Build is complete, if Rick Wood  can automate this?

 

15:00

WCI (External Team)

WCI to validate the Release Mapping Server

 

09:00SI Mapping Team

Mapping team to finalise any last mapping from the final content that came through last night, and then Resolve their "September Mapping" JIRA ticket

(eg)   https://jira.ihtsdotools.org/browse/INFRA-7423

 

12:00WCI (External Team)

FINAL MAPPING CUTOFF

This should then raise the request ticket for the Clone of Mapping content (both ICD-0/ICD-10 + GMDN) over to the Release Mapping Server, in order to provide a stable baseline for both upcoming International + GMDN releases

 

12:00Devops

Manual/automated backup of Mapping Server 

Chris Morris to automate when possible...

 

13:00WCI (External Team)

Mapping Server Cloned over to the Release Mapping Server Rick Wood did you say this needs a new server or you can re-use existing release server?

In future, this should happen immediately after the backup of the Mapping Server is complete, if this can be automated?

 

15:00WCI (External Team)

ICD-0 + ICD-10 map files are then generated by WCI and QA reports checked

Potential for some discussion with Donna if any red flags in these reports...

 

17:00WCI (External Team)ICD-0 + ICD-10 map files sent to technical team Release manager (Andrew Atkinson) before close of play

 

18:00WCI (External Team)

*** Mapping Drip feed is restarted  ***

 

02:00AutomatedMapping Drip feed runs for the first time since the initial cut off.

 

09:00SI Mapping TeamSI Mapping Team are able to re-start work for the next cycle

 

09:00SI Release TeamTechnical team Release manager builds and validates a new Pre-Production release based on the new ICD-0 and ICD-10 files

 

09:00EveryoneDR PLAN:  If there is a Critical (P1) issue found in either the Map files or the final SNOMED CT content (shouldn't be due to the new task/project validation, but we need an emergency process just in case), then WCI can import a specific fix branch straight into the Cloned Release Mapping Server, without bleed through from the next month's content.  However, this should only be used in the genuine emergency situations...