Overview

The Content team members have been working with the Observables Project Group to review, update and further progress the Observables entity Inception/Elaboration document and associated modeling details.

 2016Project ScopeDeliverablesRelease
1.

Phase 1.Inception/Elaboration document and associated modeling details.

  1. Addition and inclusion of necessary attributes and value ranges.
  2. Modeling of the existing vital sign observable content (~150 concepts).
  3. Update the Editorial Guide to include the new attributes with their domain and ranges for modeling observable entities

1,2 &3 Complete- International release schedule - Jan 2017 Release.

2017Project ScopeDeliverablesRelease
1.Phase 2. Identification of next sub-hierarchy of observables.
  1. Formalize scope of next sub- hierarchy with Internal Observable Model Implementation Project Group.
  2. Continue discussing modeling issues with the Observable Project Group
  3. Review modeled content (Internal Observable Model Implementation Project Group.)

Initiatives to be completed for the July 2017 Release

1. Complete

2. In Progress

3. In Progress

 

2.Observables Re-design Project
  1. Observation result / life phase – plans in development Currently on hold. It is a large project will require further development on tracker documentation and review. The representation of observation result also has dependency to the observation model which is still not finalized.
     
    • Phase 1 – Development, testing and documentation of Observables model (complete)
    • Phase 2 – Pilot of scalable authoring of observables content using new model (April 2016)
    • Phase 3 – Modeling of existing Observables content (January 2017)

1. The observation result part of the Observable redesign project is on hold. Please contact Daniel Karlsson, the project chair for more details.

3..Observables-upper level concept cleanup
  1. Observables -Scope of work will be dedicated to the required rework of the upper level concepts in observable hierarchy. (Previously reported under Loinc). Clean up work and modeling of existing content, some work currently under review by Head of Terminology. Approx. 4-5k concepts (2k hrs of work at a min).
  1. In Progress, resource and priority dependent - Jan 2018.