Gliffy Diagram | ||||
---|---|---|---|---|
|
The release process requires the ability for mappers to resume editing before the release cycle fully completes. Thus, this release strategy calls for completing the actual release processing on the RELEASE server and feeding back to PROD the final state of the map. Many of the steps can now be handled via the user interface, as described in this section Running the Release Process with the User Interface. A more full accounting of the original manual steps can be found in the section below entitled Mapping Tool Release Process.
...
Gliffy Diagram | ||||
---|---|---|---|---|
|
Pre-release steps
These steps will be run on PROD.
...
Gliffy Diagram | ||||
---|---|---|---|---|
|
The following are the original details to produce a release with the command line interface and manually run mojos. It still contains relevant information for running the steps that are not available through the user interface such as cloning the PROD db to the RELEASE server and the return of the produced release files back to PROD.
...