Page tree

Overview

There are sizable quality issues with this content. Some cleanup is being completed this year on the separation of the qualifier hierarchy, and then applying the corrections to the findings. To which then the content would be available for review of the TS browser before proceeding to the Jan 2017 release. With the finalization of the observables model,  we can then proceed to adding content and proceeding with content previews and releasable content. Soliciting direction and prioritization from the "Functioning Project Group"  for 2017 scope of work deliverables.

Outline

  • Disambiguation of the Interpretation value (qualifier value) hierarchy.
  • Correction of all Functional findings that erroneously use the qualifier value of "Does, not dependent".  Approximately 614 concepts.
  • There will be a targeted review distributed in early August, feedback comments to be gathered by the end of August.
  • Final approval from Jim Case, Head of Terminology for this work to be released.
  • Any corrections to be made by the close deadline for the January 2017 Release.
  • Soliciting direction and prioritization from the "Functioning Project Group"  .

 

 2016-2017Project ScopeDeliverablesRelease
1.

Phase 1 – Restructuring of existing hierarchy and identification and addition of new content (Initial work – January 2016). Function Updates to SNOMED CT International Release.

  1. Content Updates to International Release
  2. Provide updated draft of Qualifier -work
  1. Updates to Jan and July SNOMED CT International Release on yearly basis. Very minor updates to the Jan 2017 release.
    This project is considered Stopped due to the WHO focus shifting from ICF to ICD -11. Continuing would risk not having a clear direction and potential being at odds. There is also not enough substantial use cases to identify a consistent representation of Functions.
  2. Draft delivered.This project is considered Stopped due to above.

2

Phase 2 - Development, testing and documentation of concept model

  1. Concept Model Approval
  1. Not Started -June, 2017
3Phase 3 – Implementation of new model to existing functioning content content
  1. Implementation of new model
  1. Not Started -July, 2018

 



  • No labels